SCHLOUCH BEGINS DESIGN-BUILD WORK ON PHASE 2 OF CORPORATE CAMPUS AT SPRING RIDGE

SCHLOUCH BEGINS DESIGN-BUILD WORK ON PHASE 2 OF CORPORATE CAMPUS AT SPRING RIDGE

BLANDON, PA, February 2, 2000 — Schlouch Incorporated has been awarded a $1.3 million contract to handle design-build site preparation for Phase 2 of the Corporate Campus at Spring Ridge for the Peter Carlino Company.

Phase 2 consists of five commercial building lots on approximately 12 acres. According to Barry Schlouch, president of Schlouch Incorporated, his firm will design and prepare the site including reconstruction and widening of Broadcasting Road, construction of a site entrance with two ornamental ponds, fountains and decorative stone walls, handle all earthwork, install underground utilities, curb and paving.

Rik Longacre is Schlouch designer on the project. Site coordinator is Dave McGough and Rick Grant is project coordinator/estimator.